EIRE Systems provides costing, planning and coordination for technology and people relocations, and restacks of existing buildings. These relocation and restack projects have varied in size from several 10’s of users to over 1,500 users. Project deliverables have included full documentation of pre- and post-migration desktop, server and market data systems including topologies and system designs, dependency analyses, budget and cost tracking, migration scheduling, lead-time analyses, procurement procedures, risk management, implementation management, and user acceptance testing.

EIRE Systems also provides Managed Services for Moves, Adds, and Changes (MACs).

Case Study

Global Investment Bank

tokyo_skyscrapers

Client: A leading global investment bank serving institutional, corporate, government and high net worth clients, including securities underwriting, sales and trading, investment banking, private equity, alternative assets, financial advisory services, investment research, and asset management.

Project:  Relocation of main office to new building.

Solution: As part of this building relocation the following steps were implemented:

  1. IT Project Plan

    Production of preliminary Project Plan including all steps and designs necessary to successfully complete the IT infrastructure fit out in new building.

  2. IT Project Budget

    Production of  a project budget which was the main tool for IT cost management and control.

  3. IT Project Risk

    Definition of IT risks under the following headings:

    • Risk identification
    • Risk quantification
    • Risk response development
    • Risk response control

     

  4. IT Change Control Process

    Establishment of a change control process to track and incorporate changes to the scope of works, relocations schedule and costs.

  5. Establish Information Flow

    Establishment of the flow of information between all team members taking part in the relocation project to ensure that all members were informed of all relevant aspects of the projects.

  6. Resource Allocation

    Resource planning to determine whether the IT skilled resources were available internally or whether external resources were required.

  7. Requirement Analysis

    Requirement Analysis included the following tasks:

    • Gathering of existing definitions of requirements and current systems.
    • Consolidating and incorporating these requirements with future requirements (including ease of expandability, future growth, ability to incorporate future technology etc.)
    • Establishing consensus within IT and the Business on the strategic direction, specific suppliers and systems to utilise.
    • Gaining approval for the strategic and practical directions for all new IT infrastructure systems being installed in the new office.

     

  8. Design Review

    Implementation of new strategic technologies within the Client’s existing IT environment. The establishment of the new office was a very good opportunity to implement future strategic technology decisions for the Client’s core IT infrastructure.

  9. Preparation of Request For Proposal (RFP)

    The RFP process was the principal tool for vendor price negotiation. The RFP detailed all materials and labour cost required to implement the IT infrastructure, and the unit costs that could be used for any additional work outside the initial scope of works.

  10. RFP Analyses

    This process was completed by using an evaluation matrix to analyse the responses to the RFP and for making a recommendation to the Client for the supply of equipment and services.

  11. Procurement Coordination

    Working with selected vendors and the Client procurement department, the procurement process was monitored in order to prevent any potential delays to the project, which was critical when considering long lead items and where early installation was required.

  12. Liaison with Finance

    Developed a budget and cost allocation model for expenditure incurred on all IT Infrastructure works.

  13. Implementation Planning

    Produced a detailed implementation plan for the installation and deployment of all IT infrastructure, and all other systems that formed part of the scope of works for the IT infrastructure design and implementation.

  14. Site Coordination (bilingual services - English/Japanese)

    Coordination of all onsite activities of IT vendors, including arrangements such as site access, scheduling for deliveries, and procedures to be followed for building management.

  15. Site Inspection

    Implementation of daily site inspections during the construction and fit out phase, including ensuring all standards in the design and tender documentation were being adhered to.

  16. Inventory

    Coordination and validation of all the systems inventories before each user relocation.

  17. Move Coordination

    Coordination of movement of all systems and user equipment to the new building.

  18. Reinstatement of Existing Premises

    Management of removal of all non-relocated IT equipment from old IT spaces.

  19. Handover Documentation

    As part of the handover documentation the following standards were used:

    • AutoCAD for all CAD drawings
    • Microsoft Project for preparing project plans
    • Microsoft Visio for non-CAD drawings including rack layout templates etc.
    • Microsoft Word and Excel for general documentation

     

 
 